Excavation

Fencing plot. Construction of retaining walls made of stone

October 23, 2017.

Installation of doors and aluminum windows. Painting the facade

02.11.2017.

Preparation of the site for pouring draft concrete

November 9, 2017.

Pouring concrete

December 04, 2017.

Painting the facade of the house

January 12, 2018.

Installation and installation of kitchen and cabinets